The concrete structure work has been completed completely

Project Status: Under Construction
Project district: Al-Andalus
Project Type: Residential,apartment
Project delivery: 2024-06-30
Number of floors: 4
space available: 170M-185 M
Concrete structure
20 %
Interior finishes
30 %
Facade finishes and entrances
20 %

Overall Progress